Costs include Clearing, Excavation, Stone, Tarmacadam / Paving, Concrete, PC Concrete, Reinforcement, Form work, Structural Steel, Safety Barriers, Labor, Construction Equipment, Detailed Design & Construction Management / Inspection. (Accuracy +/-20%).
Major road, 2 lanes, 12’ wide each lane & 2 # 3’ wide shoulder, no bridges, N.E. USA $5.34 million per mile. $3.34 million per km.
Major road, 2 lanes, 12’ wide each lane & 2 # 3’ wide shoulder, no bridges, S.E. USA $ 6.04 million per mile. $ 3.78 million per km.
Major road, 2 lanes, 12’ each lane wide & 2 # 3’ wide shoulder including (1) 2 lane overpass bridge, S.E. USA $6.46 million per mile. $ 4.04 million per km.
Major road, 2 lanes, 12’ wide each lane & 2 # 3’ wide shoulder including (1) 2 lane overpass bridge, S.E. USA $ 6.75 million per mile. $4.22 million per km.
Addition of 12’ lane & 1 # 3’wide shoulder to existing major road in Mid-West USA. $1.43 million per mile. $0.89 million per km.
Addition of 12’ lane & 1 # 3’wide shoulder to existing major road in Central USA. $1.63 million per mile. $1.02 million per km.
Major Freeway / Interstate 4 lanes 12’ wide lane & 2 # 3’ shoulder, including (1) 2 lane overpass bridge, in N.W. USA. $19.22 million per mile. $12.01 million per km.
Major Freeway / Interstate 4 lanes 12’ wide lane & 2 # 3’ shoulder, including (1) 2 lane overpass bridge, in S.E. USA. $20.31 million per mile. $12.69 million per km.
Elevated Major Freeway / Interstate, 4 lanes 12’ wide each lane & 3’ shoulder, urban location in Central USA. $68.45 million per mile. $42.78 million per km.
Elevated Major Freeway / Interstate, 4 lanes 12’ wide each lane & 3’ shoulder, urban location in S.E. USA. $71.33 million per mile. $44.58 million per km.
For further information contact, John G. McConville CCP – Operations Director – Compass International Telephone in USA (609) 577 4505
Additional data & information can be found in our 2018 US & International Construction Costs Yearbooks that details a broad range of construction costs in the USA & 100+ countries, data includes construction labor & A/E – engineering hourly rates, construction management, bulk material unit costs, city location factors, productivity values, inflation rates, import duties / taxes, plant hire rates and much more.