Cost Data Oil & Gas

Oil and Gas Industry Benchmarking Data

Compass International details oil and gas industry benchmarks from EPC projects in the US and Canada for users. Learn about the industry here!

Compass International 3 min read
Oil and Gas Industry Benchmarking Data

The Global Construction Newsletter

**Petro-Chemical & Gas Facilities – Engineering, Procurement and Construction (EPC)**Benchmarking Data: (Data collected from 12 completed EPC projects in USA & Canada)

Typical Benchmark Percentages & Cost Ranges related to North American Petro-Chemical, Industrial & Gas Facilities. Applicable to New & Revamp CAPEX / Facility Projects with a Total Installed Cost (TIC) value between $10 million & $150 million.

NumberPercentages & RatiosLow RangeHigh Range
1Site Works as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting.0.020.045
2Concrete as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting.0.1150.165
3Structural Steel / Platforms /Siding as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting.0.1050.185
4Piping as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting.0.450.7
5Piping Material (Inside Battery Limits - ISBL & Outside Battery Limits OSBL) as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting.0.190.485
6Piping Labor (Inside Battery Limits - ISBL & Outside Battery Limits OSBL) as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting.0.41.25
7Direct Construction Labor as percent of Total Installed Cost (TIC).0.650.35
8Indirect costs (Support Labor, Field Establishment, and Construction Equipment) as percent Direct Labor Cost.0.251.25
9Piping Labor as percent Direct Labor.0.150.55
10Instrumentation Labor (Inside Battery Limits - ISBL & Outside Battery Limits OSBL) as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting.0.060.145
11Instrumentation Materials (Inside Battery Limits - ISBL & Outside Battery Limits OSBL) as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting.0.0650.165
12Electrical Labor (Inside Battery Limits - ISBL & Outside Battery Limits OSBL) as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting.0.0950.175
13Electrical Materials (Inside Battery Limits - ISBL & Outside Battery Limits OSBL) as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting.0.070.185
14Overall Major Equipment (M.E.) cost multiplier to obtain Total Installed Cost (TIC).35.5
15Buildings & Structures as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting.0.0480.113
16Off sites scope percentage of Total Installed Cost of Facility.0.150.3

Download PDF

A more detailed list of construction benchmarks, ratios and cost models is contained in our 2018 Front End / Conceptual Yearbook.

More Posts

View All Posts
Tools & Resources for Construction Cost Estimating
Cost Data Estimating Resources

Tools & Resources for Construction Cost Estimating

Gain access to free estimating tools, global cost trends and benchmarking data for construction professionals on the Compass International site.

Compass International 1 min read
CI
Cost Data Infrastructure International Publications

2022 International Costs

Compass International just released the 2022 International Infrastructure/Public Works Construction Costs and Benchmark Yearbook. Buy now!

Compass International 3 min read
CI
Cost Data

Most Expensive Cities for Construction as of June 2021

The Global Construction Newsletter The 20 most expensive international cities to construct a 4 / 5 Star Hotel or Class “A” Office Building: The average cost ...

Compass International 1 min read