**Petro-Chemical & Gas Facilities – Engineering, Procurement and Construction (EPC)**Benchmarking Data: (Data collected from 12 completed EPC projects in USA & Canada)
Typical Benchmark Percentages & Cost Ranges related to North American Petro-Chemical, Industrial & Gas Facilities. Applicable to New & Revamp CAPEX / Facility Projects with a Total Installed Cost (TIC) value between $10 million & $150 million.
| Number | Percentages & Ratios | Low Range | High Range |
|---|---|---|---|
| 1 | Site Works as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting. | 0.02 | 0.045 |
| 2 | Concrete as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting. | 0.115 | 0.165 |
| 3 | Structural Steel / Platforms /Siding as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting. | 0.105 | 0.185 |
| 4 | Piping as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting. | 0.45 | 0.7 |
| 5 | Piping Material (Inside Battery Limits - ISBL & Outside Battery Limits OSBL) as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting. | 0.19 | 0.485 |
| 6 | Piping Labor (Inside Battery Limits - ISBL & Outside Battery Limits OSBL) as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting. | 0.4 | 1.25 |
| 7 | Direct Construction Labor as percent of Total Installed Cost (TIC). | 0.65 | 0.35 |
| 8 | Indirect costs (Support Labor, Field Establishment, and Construction Equipment) as percent Direct Labor Cost. | 0.25 | 1.25 |
| 9 | Piping Labor as percent Direct Labor. | 0.15 | 0.55 |
| 10 | Instrumentation Labor (Inside Battery Limits - ISBL & Outside Battery Limits OSBL) as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting. | 0.06 | 0.145 |
| 11 | Instrumentation Materials (Inside Battery Limits - ISBL & Outside Battery Limits OSBL) as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting. | 0.065 | 0.165 |
| 12 | Electrical Labor (Inside Battery Limits - ISBL & Outside Battery Limits OSBL) as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting. | 0.095 | 0.175 |
| 13 | Electrical Materials (Inside Battery Limits - ISBL & Outside Battery Limits OSBL) as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting. | 0.07 | 0.185 |
| 14 | Overall Major Equipment (M.E.) cost multiplier to obtain Total Installed Cost (TIC). | 3 | 5.5 |
| 15 | Buildings & Structures as a percentage of Major Equipment (M.E.) cost, excludes M.E.setting. | 0.048 | 0.113 |
| 16 | Off sites scope percentage of Total Installed Cost of Facility. | 0.15 | 0.3 |
A more detailed list of construction benchmarks, ratios and cost models is contained in our 2018 Front End / Conceptual Yearbook.